PNA HQ moves forward

Signing the contract for construction of a new PNA HQ building in Majuro are, from left: PNA CEO Ludwig Kumoru and Pacific International Inc. CEO Jerry Kramer, as PNA Commercial Manager Maurice Brownjohn looks on. Photo: Rebecca Lathrop.
Signing the contract for construction of a new PNA HQ building in Majuro are, from left: PNA CEO Ludwig Kumoru and Pacific International Inc. CEO Jerry Kramer, as PNA Commercial Manager Maurice Brownjohn looks on. Photo: Rebecca Lathrop.

Parties to the Nauru Agreement’s (PNA’s) CEO Ludwig Kumoru and PNA Commercial Manager Maurice Brownjohn met with PII CEO Jerry Kramer last week for a small signing ceremony that sets the stage for a big PNA building project.

PII has already commenced demolition/site preparation work at the former Won Hai Shien/Jemen Ei Corporation facilities next to Uliga Dock.

In addition, procurement of construction materials is in progress for the planned four story building.
Meanwhile PII and PNA await the completion of the detailed design which they expect to have in another four to five weeks.
The contract value is $2,869,929.

Read more about this in the May 11, 2018 edition of the Marshall Islands Journal.